1. Mumbai Coastal Road Project PKG-2, Worli, Mumbai

Owner/Client –   Brihanmumbai Municipal Corporation (BMC) / Municipal Corporation of Greater Mumbai (MCGM)

Consultant/AMC- AECOM

Main Contractor – HCC – HDC JV (Hindustan Construction Company – Hyundai Development Corporation)

Subcontractor – M/s. International Divers Aquarium

Scope – Underwater Mooring Piles Cutting of 1m & 2m and 3 m dia. from existing sea bed level

Duration– January 2024 to February 2025

Outcome– Work Completed satisfactory

2. IOCL Captive Jetty Project Kamarajar Port Limited, Chennai , Tamil Nadu

Owner/Client –   Indian Oil Corporation Ltd

Consultant/AMC- TEPL

Main Contractor – ITD Cementation India Limited

Scope of Work– Under water Diamond Wire Saw Cutting of existing RCC Piles for “Construction of IOCL captive POL/ LPG Marine Jetty

Duration– October 2023 to July 2025 (Back to Back)

Outcome– Work Completed satisfactory

3. Underwater Diaphragm Wall Repair at Berth 3, Kakinada Port

Owner/Client – Kakinada Deep Seaport Ltd.

Consultant/AMC-  L & T Infrastructure Engineering Ltd

Main Contractor – M/s. International Divers Aquarium

Scope of Work  – Underwater Repair of the Concrete Diaphragm Wall

Duration– October 2020 to March 2021

Outcome– Quality of work found to be Satisfactory.

4. Greater Male’ Connectivity – Male’ to Thilafushi Link Project, Maldives

Owner/Client – Maldives Ministry of National Planning, Housing and Infrastructure

Consultant/AMC-  M/s. Arup Limited

Main Contractor – Afcons Infrastructure Ltd

Scope of Work – Involved in Silt Screen, Installation, Geotextile Laying, Sheet piling works, Precast concrete Blocks placing, Rock placing work and other Misc work.

Duration– June 2022 to December 2022

Outcome– Work Completed satisfactory

5. “100 MLD SWRO Desalination Plant, Dahej, Gujarat

Owner/Client – Gujarat Industrial Development Corporation (GIDC)

Consultant/AMC- 

Main Contractor – Larsen & Toubro-Tecton JV

Scope – Underwater Liner cutting and Concrete breaking.

Duration– Feb 2022 to April 2022

Outcome– Satisfactory in carrying out the Job.

6. Construction of Nouakchott Container Terminal on EPC basis at Nouakchott, Mauritania.

Owner/Client – ARISE Mauritania SA

Consultant/AMC-  EGIS International

Main Contractor – Afcons Infrastructure Limited – Mauritania

Scope – Supply of sea divers and tender divers for Nouakchott Container Terminal.

Duration– December 2019 to October 2020

Outcome– Successfully completed the scope of work

7. Underwater Beam Repairing and Groove Maintenance (RGHPCL)

Owner/Client – Rasuwagadhi Hydropower Company Limited (RGHPCL)

Consultant/AMC- 

Main Contractor – Civil Index Designing Consultancy and Construction Pvt. Ltd.

Scope – Underwater Beam Repairing and Groove Maintenance.

Duration–  October 2019 to  January 2020.

Outcome– Work Completed satisfactory

8. Hydro Power Maintenance Project-

Owner/Client – KALPAN HYDRO COMPANY (INDIA) PRIVATE LIMITED

Consultant/AMC- 

Main Contractor – Gill Acqua Hydro Power Generation Company Pvt. Ltd.

Scope – Underwater Videography, Photography and inspection and sealing of Draft Tube gates for Hydro Power Projects.

Duration– February 2019 to March 2019

Outcome– Carried out to complete satisfaction.

9. Construction Of Greenfield Port at Ramayapatnam on Engineering, Procurement and Construction Contract Basis

 Owner/Client – Andhra Pradesh Maritime Boar

Consultant/AMC-  NECL-ARIPL JV

Main Contractor – Auro Infra Private Limited (AIPL)

Subcontractor – M/s. International Divers Aquarium

Scope – X-Bloc / X-Bloc Plus placing services for Breakwater at Ramayapatnam port. Underwater Videography and inspection of placed X-Blocs below water level.

Duration– Oct 2023 to Oct 2024

Outcome– Work completed satisfactorily

10. Corrosion Protection to Quay Structures at Port Louis Harbour – Project MPA344(a)/2017

Owner/Client – Mauritius Ports Authority

Consultant/AMC- 

Main Contractor – Del Seatek India Pvt Ltd

Scope – Supply of aluminium anodes complete with fixing brackets etc for the tubular piles at Quays 1,2, 3 & 4 at Terminal II ; the sheet piles at Quays A,D,E at Terminal I; sheet piles at Trou Fanfaron and the sheet piles at Port Mathurin.Remove marine growth and scaling and prepare surfaces to receive aluminium anodes Install anodes in the quantities measured in the Bill of Quantities and as detailed in the drawings.

Duration– September 2018 to March 2019

Outcome– Work completed satisfactorily

11. Construction of Multimodal IWT Terminal at Varanasi, UP.

Owner/Client – Inland Waterways Authority of India

Consultant/AMC- 

Main Contractor – Afcons Infrastructure Ltd. Varanasi

Scope – Underwater Videography and works related to Bank Protection below River water. 

Duration– April 2018 to July 2018 & April 2019 to July 2019

Outcome– Work completed successfully

12. Kudankulam Nuclear Power Project Units-3&4 , Tirunelveli, Tamil Nadu

Owner/Client – Nuclear Power Corporation of India Limited (NPCIL)

Consultant/AMC-  AECOM

Main Contractor – Sanjay Construction Company

Scope – Underwater block placing, drilling, and blasting work.

Duration– December 2018 & October 2019

Outcome– Work Completed satisfactory

13. Construction of Coal Berth no 3& 4 – KPL

Owner/Client – Kamarajar Port Ltd

Consultant/AMC- HOWE (INDIA) PVT. LTD

Main Contractor – Afcons Infrastructure Limited

Scope of work – Underwater repairing Diaphragm wall of 450 meters length with 25 meters depth and placing Geotextile layers for slope protection works.

Duration– Feb 2017 to December 2018

Outcome– Work Completed satisfactory

14. Construction of Oil jetty Project – Liberia

Owner/Client – Arcelor Mittal Liberia Ltd.

Consultant/AMC- Royal Hoskoning DHV

Main Contractor – Afcons Infrastructure Limited

Scope of Work  – Underwater survey of damaged berth, cutting of sheet piles -100 mtr. Underwater welding -150mtr, Structural steel fit up works like brackets, vertical beams and circular beams -10 MT. Sheet pile installation and alignment – 50 MT. And grouting work.

Duration– 12 January 2013 to 31 June 2013

Outcome– Work Completed satisfactory

15. L&T Infrastructure, Hanycomb Reparing at WDFCC Pkg 15B,Gujarat

Owner/Client – WDFCC Pkg 15B

Consultant/AMC- OCG Ltd

Main Contractor – L&T Construction Ltd.

Scope of Work  – Underwater Concrete Surface Repairs of Bridge Piers.

Duration: 12 Oct  2023 to 10 Nov 2023

Outcome– Work Completed satisfactory

16. L&T Geo Structure , KPL Port RoRo Berth Reparing & Grouting work at Chennai, Tamil Naidu

Owner/Client – Kamarajar Port Limited

Consultant/AMC—Jacobs Engineering India

Main Contractor – L&T Geostructure Pvt Ltd.

Scope of Work  –  Underwater Repair of the Concrete Seaside Diaphragm Wall

Duration: 12 Oct  2023 to 10 Nov 2023

Outcome– Work Completed satisfactory

17. Project -6090-EPC-MPQ & DSO Harbour, Liberia

  Owner/ Employer- ArcelorMittal Liberial Ltd (AML)

  PMC/AMC-  Main Contractor- Afcons Infrastructure Ltd.

 Scope of Work – Offshore Activates including any underwater survey for seabed, Marine craft and Anode Install  operation etc.

Duration: 05 Feb  2025 to 30 March 2026

Outcome- Work completed satisfactorily

18. Project – Khandwa Intake Well, Charkheda Pump House, Madhya Pradesh

Owner/ Employer- Narmada Water Scheme

PMC/AMC- Mehta Consultant

 Main Contractor- CMR Infrastructure Pvt Ltd

Scope of Work: Under Water Core cutting in Intake well: 3 no.s, 1000 mm  dia   & 500 mm thick Concrete wall. Re-baring reinforcement steel.Fixing Puddle pipe 740 mm OD (with 960 mm Puddle flange OD to be grouted) Shuttering for grouting work. Grouting (Concrete mix will be supplied by us) Fixing of Sluice Gate on Flanged Puddle pipe (inside Intake) Fixing of Rose piece / Strainer on Flanged Puddle pipe (Outer side of Intake) Anchor bolting two Girders below each Port / Hole and fixing a chequered Plate on top to make a maintenance platform of say 1 m x 1.5 m.

Duration: 01 May 2025 to 18 Sep 2025

Outcome- Work completed satisfactorily

                            

19. Project – Jal Jeevan Mission-Uttar Pradesh

 Owner/ Employer- JWIL

PMC/AMC- Main Contractor- CMR Infrastructure Pvt Ltd

Scope of Work: 1) Under Water Core cutting in Intake well: 2 no.s, appx. 1150 mm dia (or square) in 750 mm Concrete deep.

2) Re-baring reinforcement steel 16 mm dia

3) Fixing Puddle pipe 945 mm OD (with 1115 mm Puddle flange OD to be grouted)

4) Shuttering for grouting work.

5) Grouting

Duration: 10 Dec  2022 to 14 Feb 2023

Outcome- Work completed satisfactorily

20. Project - Engineering, Procurement, Fabrication, and Installation of Second Liquid Cargo Berth at GCPL, Dahej, Gujarat

Owner/ Employer Gujarat Chemical Port Limited (GCPL)                                 

PMC/AMC-RPMG

Main Contractor- Afcons Infrastructure Ltd.

Scope of Work –Carry Out the zero-level pile cutting and  any underwater works instructed by the Site engineer for the aforesaid project for Engineering, Procurement, Fabrication, and Installation of Second Liquid Cargo Berth.

 Duration:  Oct 2025 to Feb 2026

Outcome- Work completed satisfactorily

21. Cooling Tower Construction Project 20-2I0005, NTPC LTD, Super Thermal Power Station. Rihandnagar21. Cooling Tower Construction Project 20-2I0005, NTPC LTD, Super Thermal Power Station. Rihandnagar

Owner/Client –   NTPC – Rihandnagar

Consultant/AMC- ………..

Main Contractor – PAHARPUR COOLING TOWERS LIMITED

Subcontractor – M/s. International Divers Aquarium

Scope – Underwater Interconnection of CW Channel with the existing channel work by Diamond wire cutting.

Duration– 10 Feb 2023 to 24 Feb 2023

Outcome– Work Completed satisfactory

22. Construction of Major High Level Bridge across Wainganga River at Ambhora,Nagpur.

Owner/Client –   NHAI

Consultant/AMC-

Main Contractor – T&T Infra Ltd

Scope of Work– Underwater Welding of some74 Brackets of Bracket 400mm 27.5Kg and Bracket 300mm 23.15kg and Underwater Bracket Cutting of some 12 piles for Pile Cap Shuttering/Stagging Work for High Level Stay Cable Bridge Construction

Duration: 3 April 2021 to 21 April 2021

Outcome– Work completed satisfactorily

23. Bhama Askhed Jack Well Project

Owner/Client –  Pimpri Chinchwad Municipal Corporation (PCMC)

Consultant/AMC-  DRA Consultants Pvt. Ltd.

Main Contractor – T&T Infra Ltd

Scope of Work  –  Underwater drilling and blasting with all underwater tools and tackles, consumable items, etc. And relevant manpower for Underwater Intake Channelat Bhama River dam (Qty 1589 CUM)

Duration: 15 May 2024 to 31 July 2024

Outcome– Work completed satisfactorily

24. NH-4 PACHWADESHWAR KODOLI River Bridge Project

Owner/Client – NHAI

Consultant/AMC-  ……..

Main Contractor – T&T Infra Ltd

Scope of Work  – Underwater bracket welding of liner piles with all underwater tools and tackles, consumable items, manpower, etc.,for pile cap shuttering/stagging work

Duration: 02 April 2024 to 28 April 2024

Outcome– Work completed satisfactorily

-->